Even -30C can not stop ROXON to serve our clients.

ROXON Gällivare service team together with project organization successfully executed planned upgrades on client’s existing conveyor line in the middle of winter, facing extra challenge of temperature dropping down to -30C outside. After 5 days mill maintenance shut down new diverter chute is ready to feed material to ROXON’s new pebble crushing line where silo, belt feeders and high incline conveyor are waiting.

On ROXON’s project there are 2 similar pebble crushing lines, which are fed from old milling circuit conveyors via diverter chute. During shut down numerous other modernizations were done to existing conveyors as well like upgrading a conveyor to run both directions, belt scale installation, metal detector installation, emergency chute relocation, new loading point installation, skirt board upgrades, spillage tray and safety guard modifications just to name few.